LANDING STATIONS
SEDILI
batam
jakarta
BALIKPAPAN (optional)
DAVAO
GUAM
HAWAII (optional)
florence, oregon usa
SPECIFICATIONS
Designed for 25 years
Open Cable System
16 Fiber Pairs
Minimum 15 Tbps per Pair
Repeatered System
Reconfigurable BUs
High reliability – Double-end power Feeding with Single -end capability
Wet & Dry Plant – World class architecture,design & manufacture
Deployment – World class Marine Installer
myus DEPLOYMENT PROGRAM RFS Q4 2028
-
BUSINESS DEVELOPEMENT PROGRAM
24 Month
Q4 20-Q3 23
By HEXA
-
FEASIBILITY AND DESKTOP STUDY (DTS)
12-15 Month
Q4 23-Q1 25
By USTDA Grant
-
PRE- IMPLEMENTATION (PMC)
6-12 Month
Q2 25-Q3 25
-
IMPLEMENTATION OF WET AND DRY PLANT (RFS)
36 Month
Q4 25-Q4 28
By Assigned Vendor
-
OPERATION AND MAINTENANCE (O&M)
240 Month (20 years)
2028 - 2048
By HEXA O&M